Description of the Works
Contractor - Graham’s have requested the use of Gate 3 to remove spoil and receive concrete deliveries during the civils works (installation of service trenches for the water mains and LV electrical cable) being carried out across the Gate 1 which is their normal access.
The works will be carried out over a 4day period detailed below.
Graham’s will provide traffic control personnel to control vehicle movements coming out of Gate 3 and around past Faulker/Eggington and then also on the tight bend by Stewart Mason building.
Please take extra care when using the both the road and pavement during this period.
Timescale
Friday 13/11/2026:
- Muck away collection x 40 (08:00 start, 16:00 finish)
- Concrete 3 Loads + (15:00 start, 17:30 finish)
Monday 16/11/2026:
- Muck away collection x 40 (08:00 start, 16:00 finish)
- Concrete 3 Loads + (15:00 start, 17:30 finish)
Friday 20/11/2026:
- Muck away collection x 40 (08:00 start, 16:00 finish)
- Concrete 3 Loads + (15:00 start, 17:30 finish)
Monday 23/11/2026:
- Muck away collection x 40 (08:00 start, 16:00 finish)
- Concrete 3 Loads + (15:00 start, 17:30 finish)
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Name and Job Title: Tim Oakey Project Manager