Description of the works
A new Submain is to be installed from Rutland Lodge (DB34) and terminated within a newly installed distribution board (DB1) in the Nursery storeroom.
The installation is required as part of an upgrade to replace the currently heavily overloaded single-phase supply and Distribution board.
Timescale
Phase 1. Installation of new submain will be w/c 17 August 2026
Phase 2. Installation of new Distribution board will be completed over the weekend of 22-23 August 2026