Fine Art (041) & 3D Design (038) - Fire Alarm Installation Works - 11th & 12th February 2026.

Posted: 28 January 2026

DESCRIPTION OF THE WORKS

Fine Art – A new fire alarm device required in Ground Floor Room 0.39 Office. To be wired from Room 0.38B Display/Studio. The installation works will require drilling and space for the engineers to work. Works will take all day but engineers can move out of the way if access is required through, or in/out of the rooms for short periods.

3D Design – Two new fire alarm devices are required. One in the Knitting Studio Office Room 0.05 and one in the Cleaners Cupboard (no number available). The installation works will require drilling and space for the engineers to work. Works will take half a day per device but engineers can move out of the way for short periods for access as required.

TIMESCALE

Fine Art – Wednesday 11th February 2026 – 08:00 – 16:00

3D Design – Thursday 12th February 2026 – Cleaners – 08:00 – 12:00

3D Design – Thursday 12th February 2026 – Office – 12:00 – 16:00

How can I get more information and help?

The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.

Name and Job Title: Edward Roe. Fire Alarm Engineer for BTS.

Mobile: 07884 237879.

Email:  Edward@buildingtechnologyservices.co.uk