Description of the Works
CAP Project
The portacabins which will house the site huts for the new CAP project will be delivered on Monday 20th July, This will be at site entrance 1 on Margaret Keay Road, and will involve the closure of this site entrance, There is a slab concrete pour taking place also on Monday and the concrete lorries will divert around the front of Brockington and enter the site via gate 3 at Morag Bell this will be for 2 days only.
Timescale
20th-21st July 2026. (07:30-18:00)
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Name and Job Title: David Bell
Mobile: 07729080152
Email: d.w.bell@lboro.ac.uk