Description of the Works
3D Design (038)
The existing 2no. gas fired water heaters are to be converted to a sealed system installation configuration, this will involve the alteration of the cold feed pipework including installation of new check valves and flow through expansion vessels. The existing cold feed pipework is to be cryogenically frozen to allow the installation of new isolation valves which are to be used to individually isolate each tank while the works take place.
This work is necessary is to improve water quality by eliminating the current back feeding of the circulated return hot water through into the buildings cold water supply.
As there are 2no. water heaters the pipework conversion will take place independently to each tank to ensure hot water remains available to the building throughout the works. Building users may notice reduced tap outlet temperatures during peak demand, this will be due to the temporary decrease in available hot water volume/supply capacity.
Timescale
Friday 27 November to Friday 4 December 2026
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Name and Job Title: Aaron Smart – Mechanical Building Services Engineer
Mobile: 07989420705
Email: a.j.smart@lboro.ac.uk