NCSEM (210) - Quarterly Fire Alarm Maintenance (Visit 1 /4) - 14/10/25

Posted: 9 October 2025

DESCRIPTION OF THE WORKS

This is the first of four visits to test the fire alarm system in the above mentioned building(s).

The test will be carried out silently with no intentional activation of the fire alarm sounders or associated interfaces.

Access will be required to all areas of the building with the keys (usually) obtained from FM.

The fire panel will be regularly monitored by BTS for activations that are not part of the test.

Any activations that are heard should be treated as real.

     

TIMESCALE

14/10/25 -- 07:30 – 16:00

How can I get more information and help?

The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.

Name and Job Title…Edward Roe. Fire Alarm Engineer for BTS.

Mobile:  …07884 237879.

Email: …Edward@buildingtechnologyservices.co.uk