Morag Bell - Handwashing & Air-Conditioning Installation - Various dates.

Posted: 1 April 2026

Description of the Works

Works inc. installation of handwashing facilities and air-conditioning across all the labs, alongside installing a ceiling and other minor builders works (inc. making necessary service adjustments) in E025/E029.

Works are essential to maintain lab safety and human comfort.

End users can expect intermittent noise from contractors and small power tools.

Timescale

E025 & E029  - 13 April - 8 May 2026 Combined 

E015 - 11 May - 29 May 2026

E015A - 1 June -18 June 2026

E030 - 22 June 2026 onwards 