Description of the works
To carry out works within each ensuite pod within Cayley 4 to allow the E&FM Mechanical Maintenance team to maintain the infrastructure for the future.
This will include:
New access hatch installation
Pipework alterations
New toilet cistern
New toilet connections
New pod doors
New pod door thresholds
Timescale
9 - 16 September 2025
How Can I Get More Information and Help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced as a result of these works.
Matthew Polkey - Mechanical Maintenance Manager
Mobile - 07895331869
Email - m.polkey@lboro.ac.uk