Description of the Works
This is the first of four visits to test the fire alarm system in the buildings listed below.
The test will be carried out silently with no intentional activation of the fire alarm sounders or associated interfaces.
Access will be required to all areas of the building with the keys (usually) obtained from E&FM.
The fire panel will be monitored by BTS for activations that are not part of the test.
Any activations that are heard should be treated as real.
Buildings involved are:
Frank Gibb Teaching (023)
Frank Gibb Labs (024)
John Pickford (033)
STEM (219)
West Park Teaching Hub (217)
ATIC (220)
Michael Pearson East (078)
Michael Pearson West (079)
Timescale
10 December 2025
8.00 a.m. - 11.00 a.m. - Frank Gibb Teaching
11.00 a.m. - 1.30 p.m. - Frank Gibb Labs
1.30 p.m. - 4.00 p.m. - John Pickford
11 December 2025
8.00 a.m. - 1.00 p.m. - STEM
1.00 p.m. - 4.00 p.m. - West Park Teaching Hub
12 December 2025
8.00 a.m. - 11.00 a.m. - ATIC
11.00 a.m. - 12.30 p.m. - Michael Pearson East
1.00 p.m. - 3.00 p.m. - Michael Pearson West
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Edward Roe - Fire Alarm Engineer for BTS
Mobile: 07884237879
Email: Edward@buildingtechnologyservices.co.uk