FACILITIES MANAGEMENT - NOTICE OF MINOR WORKS

W BUILDING (SIR DAVID DAVIES)
Commissioning/Witnessing of New Fire Alarm System
Wednesday 31st January 2018, Thursday 1st February 2018 and Tuesday 6th February 2018

SPECIFICS OF THIS NOTICE:
As part of the works to refurb W building we need to replace the fire alarm system. As the newly refurbished areas are handed back we need to commission/fully prove the operation of these parts of the system. We are now nearing completion for areas of W.2, W.0 & W. roof.

TIMESCALE?
The current works are planned for Wednesday 31st January 2018, Thursday 1st February 2018 and Tuesday 6th February 2018 between the hours of 6.30pm and 8.30pm

HOW WILL THE WORKS AFFECT ME?
The detection will be activated and sounders will operate for long periods during the times stated but no LU Staff/Students must be in W building during these times. We also ask that all Staff/Students within S building take note of this work as they may hear the sounders etc. if located in rooms/areas adjacent to the W/S link bridge.
NB. The fire alarm system incorporates several sounders on the roof area which will be clearly heard from surrounding buildings such as Burleigh Court, KGB, STEM and possibly David Collett. Again, please be aware of this planned works.

HOW CAN I GET MORE INFORMATION AND HELP?
The Project Manager/Clerk of Works from Facilities Management dealing with this project are detailed below, they will be pleased to assist in any way possible and practicable with difficulties you experience as a result of these minor works.
The LU project team apologise for any inconvenience this may cause, the times / dates selected were deemed the most suitable.

Project Manager – Shaun Green(S.J.Green@lboro.ac.uk Phone 07971636268).
Clerk of Works – David White (D.A.White@lboro.ac.uk. Phone 07971333004).

HEALTH AND SAFETY
All other electrical systems will operate as per normal but the contractors will need to access areas still under the control of LU and occupied by LU Staff/Students.